Project Manager / Theo Marquardt

Coordinate. Sequence. Anticipate.

Keep dependencies in flow. Surface risk before it bites. Move the timeline only when it must move.

Stage · ExecutionAt risk13 open1 blocked13 overdue
Project
Project Manager
Project
Altbau Mitte
Linienstraße 142, 10115 Berlin-Mitte
Client
Familie Hoffmann
Handover 2026-10-01
Programme
Week 11 / 29
Started 2026-03-18
Critical path
Skim & prime north wall
Blocked · Living room

Budget

43%
Planned
€184.000
Committed
€124.000
Spent
€78.400

Deliveries carrying cost

  • Kalkfarbe, warmweiß (18 buckets)
    Kreidezeit · 2026-06-06
    Confirmed
  • Küchenkorpusse, Eiche
    Tischlerei Nord · 2026-06-11
    Scheduled
  • Eiche Dielen, 220 mm
    HolzLand Berlin · 2026-06-18
    Scheduled
  • Calacatta Marmor, Küchenblock
    Stoneline Berlin · 2026-07-02
    Delayed